WhiteFiber Signs $300M Term Loan for NC-1 Data Center, No Funds Drawn Yet
WYFI sits 31% above its 52-week low of $7.43.
Summary
WhiteFiber's NC-1 project subsidiaries signed a $300 million term loan ($200M initial, $100M delayed-draw) with Morgan Stanley as agent, but no funds are drawn — initial funding depends on the first 40MW being ready and customer-accepted.
Updates
· Reuters — Initial loans amortize quarterly at 2.5% of principal starting Q1 2027, and both facilities mature five years after initial funding.
Key Events · Financing and Capital Events · WYFI
-
Project Subsidiaries Sign $300M Term Loan
Enovum NC-1 Midco and Bidco entered a Term Loan Credit Agreement on November 9, 2026 with Morgan Stanley Senior Funding as administrative and collateral agent, providing $300.0 million of commitments: a $200.0 million initial term loan and a $100.0 million delayed-draw facility.
-
No Funds Drawn; Conditions Precedent
As of the report no loans had been funded. Initial funding requires readiness and customer acceptance of the first 40MW at the NC-1 data center and is scheduled within 30 days of closing, subject to up to two successive 30-day extensions; delayed-draw requires final completion of the first 40MW phase plus pro forma financial tests.
-
Pricing and Amortization Terms
Loans bear Term SOFR (2.00% floor) plus 6.00%, or base rate (3.00% floor) plus 5.00%, with an extra 2.00% during an event of default. Both facilities mature five years after initial funding and amortize quarterly at 2.50% of principal, starting with the quarter ending March 31, 2027 for the initial term loan.
-
Covenants Start March 2027; Parent Not a Guarantor
Beginning with the test period ending March 31, 2027, the Borrower must maintain a minimum debt service coverage ratio and a maximum debt-to-net-operating-income ratio, subject to equity-cure rights. Holdings guarantees the obligations and the loans are secured by substantially all Borrower/Holdings assets plus a mortgage on the NC-1 data center; WhiteFiber, Inc. does not guarantee the loans.
Analysis · WYFI · Crypto Assets
WhiteFiber's project subsidiaries have locked in a $300 million term loan from a Morgan Stanley-led lender group to fund Phase 1 construction of the NC-1 data center in Madison, North Carolina. The structure is what matters here: $200 million is available at initial funding and $100 million is delayed-draw, and nothing has been funded yet. Initial funding hinges on the first 40MW of capacity being ready and accepted by the customer, with a 30-day window after closing that can stretch by up to two more 30-day extensions. This is debt at the project level, not the parent: the loans are secured by the Borrower's and Holdings' assets plus a mortgage on the NC-1 data center, and WhiteFiber, Inc. does not guarantee them. That keeps the obligation off the parent's balance sheet in a guarantee sense, but the covenants (minimum debt service coverage and maximum debt-to-NOI starting with the test period ending March 31, 2027) and the make-whole/prepayment premiums constrain flexibility. Pricing is expensive — Term SOFR plus 6.00% with a 2.00% floor — consistent with a construction-stage project loan. It follows the $310 million convertible notes closed in August 2026 and the $60 million North Carolina site purchase closed November 3, 2026, so the company is now layering project debt on top of corporate converts to build out capacity.
How filings like this one have moved
In the 30 days to Nov 10, 2026, 36.4% of the 3168 measured filings Wiseek scored 7 moved their stock by 5% or more by the next session's close. The median move was 0.00%. These are measured outcomes after filings of this importance, not a forecast for this one.
Measured one observation per ticker per day, after exclusions. Current figures: Filing Impact Tracker · open dataset
At the time of this filing, WYFI was trading at $9.75 on NASDAQ in the Crypto Assets sector, with a market capitalization of approximately $433.3M. The 52-week trading range was $7.43 to $46.87. This filing was assessed with neutral market sentiment and an importance score of 7 out of 10.