Namib Minerals Reports Advanced Progress on How Mine Mill Expansion Project
Summary
Namib Minerals announced significant progress on its Mill Expansion Project at How Mine, with civil works completed and key equipment delivered, keeping the project on track for H2 2026 completion.
Key Events
-
Mill Expansion Project Progress
Civil works for the Mill Expansion Project at How Mine are at an advanced stage, with raft foundation, mill plinth, and tower foundations completed.
-
Key Equipment Delivered
Principal mechanical components, including the mill shell, have been delivered to the site, and factory acceptance tests for power components are complete.
-
Project On Track
The company remains on schedule to complete construction and commissioning of the expansion project in H2 2026, as previously communicated.
Analysis
This operational update provides positive news on a critical growth initiative for Namib Minerals. The How Mine Mill Expansion Project, aimed at increasing gold output, is progressing as planned with significant civil works completed and key equipment delivered. This update helps to counter recent negative disclosures regarding internal control weaknesses and production declines, demonstrating execution on strategic projects.