Fermi's Q3 10-Q carries a going-concern warning: $286.3 million of cash against a $2-3 billion near-term capex plan, a $356.1 million nine-month net loss, and debt that jumped to $999.9 million. The TensorWave lease was terminated and replaced only by a non-binding 600 MW hyperscaler LOI.
Key Events · Earnings and Guidance · FRMI
-
Going-Concern Warning Disclosed
Cash and cash equivalents of $286.3 million plus $29.2 million restricted cash are not sufficient to satisfy obligations within one year absent management's plans, which include undrawn equipment facilities, asset monetization, and sequencing capex to signed tenant deals.
-
Nine-Month Loss and Cash Burn
Net loss of $356.1 million for the nine months ended September 30, 2026, with $110.6 million of operating cash used and $759.5 million invested in property, plant, and equipment.
-
Debt Jumps to $999.9 Million
Total debt rose from $148.9 million at December 31, 2025 to $999.9 million, including $431.3 million of 5.00% convertible notes due 2031 with a $9.52 conversion price — far above the current $2.07 share price.
-
TensorWave Lease Terminated
The TensorWave lease's October 31, 2026 closing date passed without extension and the lease was terminated November 10, 2026; the replacement is a non-binding LOI with an investment-grade hyperscaler for ~600 MW plus a $200 million prepayment and $15 million early construction agreement.
Analysis · FRMI · Real Estate & Construction
Fermi has no revenue and burned $110.6 million of operating cash in nine months while spending $759.5 million on Project Matador construction, leaving $286.3 million of cash and $29.2 million restricted. Management states plainly that these resources are not sufficient to meet obligations within one year absent its plans — undrawn equipment facilities, asset monetization, and sequencing capex to signed tenant deals. Debt has ballooned to $999.9 million from $148.9 million at year-end, including $431.3 million of 5.00% converts struck at $9.52 versus a $2.07 stock price, so conversion is far out of the money and the notes are a cash obligation. The material weakness in internal controls persists, and the company disclosed an EDNY subpoena and an SEC document request covering Project Matador and former management. The TensorWave lease — the anchor of the earlier $6.5 billion contracted-revenue story — was terminated November 10, 2026, and the replacement is only a non-binding LOI with an investment-grade hyperscaler for 600 MW, backed by a $200 million prepayment and $15 million early construction agreement. The next hard deadlines are the December 31, 2026 TTU notice-to-proceed and High Voltage customer-agreement dates and the February 10, 2027 project-financing covenant under the Turbine Warehouse facility.
How filings like this one have moved
In the 30 days to Nov 12, 2026, 47.3% of the 1873 measured filings Wiseek scored 8 moved their stock by 5% or more by the next session's close. The median move was -0.17%. These are measured outcomes after filings of this importance, not a forecast for this one.
Measured one observation per ticker per day, after exclusions. Current figures: Filing Impact Tracker · open dataset
At the time of this filing, FRMI was trading at $2.07 on NASDAQ in the Real Estate & Construction sector, with a market capitalization of approximately $1.3B. The 52-week trading range was $1.44 to $22.37. This filing was assessed with negative market sentiment and an importance score of 8 out of 10.