NCUC Approves Duke Energy Carolinas and Progress Rate Settlements at 9.8% ROE
DUK sits 15% above its 52-week low of $112.4.
Summary
North Carolina regulators approved Duke Energy's Carolinas rate settlements at a 9.8% ROE — far below the 10.95% originally requested — with combined two-year revenue increases of $834 million versus $1,731 million sought. The orders also create a data center tariff with 15-year minimum contracts for large loads.
Updates
· Seeking Alpha — Approved rates allow average annual increases of 3.7% for Duke Energy Carolinas and 3.4% for Duke Energy Progress, with residential increases averaging 4.8% and 4.7%.
- Household Bill Impacts — Eastern North Carolina and Asheville household bills rise 9.3% over two years, while Western North Carolina household bills rise 9.5% over two years.
- Typical Customer Bills — A Duke Energy Progress customer using 1,000 kWh per month pays $9.62 more starting January 1, 2027, and $5.89 more starting January 1, 2028; Duke Energy Carolinas bills rise $6.53 and then $4.66 on the same dates.
- Data Center Tariff — A new rate schedule applies to data center customers above 50 MW, with upfront dedicated facility payments, transmission upgrade financial requirements, and security provisions tied to stranded generation risk.
All 6 details
- Eastern North Carolina and Asheville household bills rise 9.3% over two years.
- Western North Carolina household bills rise 9.5% over two years.
- Duke Energy Progress customer using 1,000 kWh per month: monthly bill increases $9.62 starting January 1, 2027, and an additional $5.89 starting January 1, 2028.
- Duke Energy Carolinas typical customer using 1,000 kWh per month: monthly bills rise $6.53 starting January 1, 2027, and by another $4.66 starting January 1, 2028.
- Data center schedule includes upfront dedicated facility payments and transmission upgrade financial requirements.
- New rate schedule for data center customers above 50 MW, including upfront dedicated facility payments, transmission upgrade financial requirements, and security provisions tied to stranded generation risk.
Key Events · Product Development and Regulatory · DUK
-
NCUC Approves Carolinas Rate Settlements
Orders issued November 16, 2026 approve the Comprehensive Settlements for Duke Energy Carolinas and Duke Energy Progress, with revised customer rates expected effective January 1, 2027.
-
Allowed ROE Cut to 9.8%
The approved 9.8% return on equity with a 53% equity component is below the 10.95% originally requested and the 10.48% in rebuttal testimony, reducing allowed earnings on the retail rate base.
-
Revenue Increase Roughly Halved
DEC's two-year revenue requirement increase is $496 million (7.4% combined) versus $1,002 million requested; DEP's is $338 million (6.8% combined) versus $729 million requested — $834 million combined against $1,731 million sought.
-
Data Center Tariff Established
A DC Schedule requires minimum 15-year contracts for data centers over 100 MW, 75% minimum billing demand, curtailment provisions, construction contributions, letters of credit and stranded generation charges.
Analysis · DUK · Energy & Transportation
North Carolina regulators finalized the rate cases for Duke's two Carolinas utilities, and the outcome is materially worse for earnings than what the company asked for. The approved 9.8% return on equity is well below the 10.95% originally requested and the 10.48% in rebuttal testimony, and the combined revenue requirement increase of $834 million over two years is roughly 52% below the $1,731 million originally sought. That gap is the core of the story: Duke absorbs the cost of its capital program at a lower allowed return, which pressures the earnings and dividend coverage that a $100B+ utility is valued on. Offsetting that, the orders give Duke something it wanted on data centers — a dedicated DC Schedule with 15-year minimum contracts for loads over 100 MW, 75% minimum billing demand, construction contributions and stranded-generation charges — which improves the credit quality of the large-load growth pipeline. The two $10 million pre-tax charges are excluded from adjusted earnings, so they do not change guidance. Revised rates take effect January 1, 2027, and the company will evaluate a rate case stay-out until at least November 1, 2028 if regulators allow deferral of the Person County CC1 and Marshall CT costs.
How filings like this one have moved
In the 30 days to Nov 15, 2026, 48.2% of the 1980 measured filings Wiseek scored 8 moved their stock by 5% or more by the next session's close. The median move was -0.20%. These are measured outcomes after filings of this importance, not a forecast for this one.
Measured one observation per ticker per day, after exclusions. Current figures: Filing Impact Tracker · open dataset
At the time of this filing, DUK was trading at $129.74 on NYSE in the Energy & Transportation sector, with a market capitalization of approximately $101.8B. The 52-week trading range was $112.40 to $134.49. This filing was assessed with negative market sentiment and an importance score of 8 out of 10.