Caledonia Q3 Revenue Up 10.5% to $78.9M; Profit Down 39% on Non-Cash Derivative Loss
CMCL sits 26% above its 52-week low of $15.85.
Summary
Caledonia's Q3 revenue rose 10.5% to US$78.9 million on a higher gold price, but profit fell 39% to US$11.3 million on a non-cash US$12.9 million derivative remeasurement. Blanket production missed and 2026 guidance was cut, with October output of 6,940 oz suggesting the compressor fix is working.
Key Events · Earnings and Guidance · CMCL
-
Q3 Revenue Up 10.5% to $78.9M
Revenue rose to US$78.9 million from US$71.4 million on a realised gold price of US$4,134/oz versus US$3,434/oz, and gross profit climbed 13.6% to US$41.9 million.
-
Profit Falls 39% on Non-Cash Derivative Loss
Profit after tax dropped to US$11.3 million from US$18.7 million after a US$12.9 million non-cash fair value loss on the convertible note conversion derivative and gold put options; the embedded derivative liability rose to US$37.4 million from US$27.4 million as the share price moved from US$19.10 to US$23.54.
-
Blanket Guidance Cut on Production Miss
Blanket produced 17,030 oz, down 11%, on compressed-air shortages and roughly 1,100 oz of gold trapped in the plant; 2026 guidance is now 69,000-72,500 oz with AISC of US$2,650-US$2,850/oz sold.
-
October Output of 6,940 oz After Fixes
Delayed compressors were commissioned October 31 and a new elution vessel on October 16; October production was 6,940 oz at a 2.95 g/t grade, with over half the locked-up gold recovered by November 6.
Analysis · CMCL · Energy & Transportation
Revenue and gross profit both rose on a much stronger gold price (US$4,134/oz vs US$3,434/oz), yet reported profit fell 39% to US$11.3 million. The culprit is a US$12.9 million non-cash mark-to-market loss on the convertible note conversion derivative and gold put options, driven mainly by the share price rising from US$19.10 to US$23.54 over the quarter. That is an accounting swing, not cash leaving the business: operating cash flow was steady at US$13.6 million and total liquidity stands at US$196.1 million. The real operational issue is Blanket, where compressed-air shortages and a plant gold lock-up cut production 11% to 17,030 oz and forced 2026 guidance down to 69,000-72,500 oz with AISC up to US$2,650-US$2,850/oz sold. Management says the compressors were commissioned October 31 and October output was 6,940 oz, so Q4 is the test of whether the fix holds.
How filings like this one have moved
In the 30 days to Nov 12, 2026, 37% of the 3595 measured filings Wiseek scored 7 moved their stock by 5% or more by the next session's close. The median move was 0.00%. These are measured outcomes after filings of this importance, not a forecast for this one.
Measured one observation per ticker per day, after exclusions. Current figures: Filing Impact Tracker · open dataset
At the time of this filing, CMCL was trading at $20.00 on NYSE in the Energy & Transportation sector, with a market capitalization of approximately $386.7M. The 52-week trading range was $15.85 to $34.00. This filing was assessed with neutral market sentiment and an importance score of 7 out of 10.