CleanSpark Posts $987.1M Fiscal 2026 Net Loss as Bitcoin Mining Revenue Falls 25%
CLSK is trading near its 52-week low of $4.835 (5.8% above the low).
Summary
CleanSpark lost $987.1 million in fiscal 2026 as bitcoin mining revenue fell 25%, while taking on $2.28 billion of secured debt to build the Sandersville AI data center that won't produce rent until November 2027.
Key Events · Earnings and Guidance · CLSK
-
Fiscal 2026 Net Loss of $987.1M
Revenue fell 25% to $576.5 million from $766.3 million as bitcoin averaged $79,678 versus $97,337 a year earlier; net loss was $3.74 per basic share versus $1.25 of income in fiscal 2025.
-
Non-Cash Charges Dominate the Loss
Impairment expense of $177.1 million (including $154.0 million on the Sandersville asset group) plus a $281.6 million bitcoin fair-value loss and $428.2 million of depreciation drove the loss; Adjusted EBITDA was negative $304.2 million versus positive $823.4 million a year ago.
-
$2.28B Secured Notes Fund the Pivot
CSDC Finance issued $2,276.0 million of 7.875% senior secured notes due 2031 at 98.5% of par (8.61% effective rate); total debt is now $4.18 billion gross against $786.0 million of stockholders' equity, with principal installments expected to begin October 1, 2028.
-
Sandersville Lease Worth ~$6.56B Over 20 Years
The triple-net lease covers 175 MW with total contractual rent of approximately $6,560,000 thousand over the initial term; lease commencement is expected November 2027 and the Data Center Infrastructure segment recorded zero revenue in fiscal 2026.
Analysis · CLSK · Crypto Assets
CleanSpark's first full year as a two-segment company shows the cost of the pivot: revenue fell 25% to $576.5 million as bitcoin averaged $79,678 versus $97,337 a year earlier, and the company swung from $364.5 million of net income to a $987.1 million loss. Roughly $177.1 million of that is non-cash impairment from retiring Sandersville mining assets and culling inefficient miners, and another $281.6 million is a mark-to-market loss on bitcoin holdings — neither is cash leaving the business. The real story is the balance sheet transformation: $2.28 billion of 7.875% secured notes now fund the Sandersville AI data center, pushing total debt to about $4.18 billion against $786.0 million of equity, with the first principal installments not due until October 2028 and lease revenue not starting until November 2027. Until that rent begins, the company is servicing roughly $180 million of annual interest while mining economics deteriorate — and management just cut the probability of hitting its 2026 data-center leasing targets to zero because of Texas moratoriums.
At the time of this filing, CLSK was trading at $5.11 on NASDAQ in the Crypto Assets sector, with a market capitalization of approximately $1.3B. The 52-week trading range was $4.84 to $19.17. This filing was assessed with negative market sentiment and an importance score of 8 out of 10.